How early should planning for a special crossing begin?
As early as possible. Approval processes with Deutsche Bahn or Autobahn GmbH often take six months or longer. If you wait to plan special crossings until the rest of the route is complete, you risk significant project delays. We recommend identifying special crossings first and including them in the preliminary planning immediately.
What drilling method is used for special crossings?
That depends on the obstacle, the length of the crossing, and the ground conditions. Horizontal directional drilling (HDD) is the most common method used for crossing rail lines, highways, and bodies of water. For shorter distances or under certain soil conditions, push drilling or microtunneling may also be used. We select the method based on technical and economic criteria.
Who approves a special crossing?
That depends on the type of obstacle. Deutsche Bahn AG is responsible for railroad crossings; Autobahn GmbH des Bundes for highways; the respective state highway authority for federal highways; and the relevant water authority for bodies of water. We are familiar with the requirements and processes of the various agencies and will handle the entire application process for you.
How much does a special crossing cost?
Costs vary greatly depending on the type of crossing, length, drilling method, and the requirements of the responsible authority. Railroad crossings are among the most complex and expensive special crossings, as they are subject to particularly strict technical specifications and require external expert opinions. We will provide you with a reliable cost estimate based on the specific route conditions.
Can netzkontor nord take on special crossings even while a project is already underway?
Yes. We also step in when a project is already underway and certain special crossings are still pending. We quickly get a sense of the current status, identify the critical issues, and bring the process to a structured conclusion.
Complex Crossings Without Delay
Talk to our team. We’ll review your route and let you know which crossings are critical, how long the permitting process typically takes, and what steps to take to ensure your project isn’t held up by a railroad crossing.