- Legally required notice of installation with sufficient advance notice
- Cover letter, proposed appointment, reminder, and follow-up
- Availability via phone, email, and online appointment scheduling, so the customer can choose the channel they already use
- In apartment buildings, reach out through property management, building superintendents, and housing management companies
- Grouping appointments by street and building rather than by date received
- Route planning with realistic travel times and buffers for special cases
- Last-minute rescheduling in case of cancellations to keep the day on track
- Coordination with parallel activities in the grid, such as meter replacement or grid connection work
- Defined escalation process with documented attempts to contact the customer
- Notification cards with a callback option and a self-booking link
- Clearly documented evidence in the event that a measurement point cannot be equipped
- Preliminary assessment of whether the meter location is even suitable
- Identification of metering points with transformer-based metering, special billing, or restricted access
- Identification of facilities under Section 14a of the Energy Industry Act (EnWG) and generation facilities that require different technology
- Daily and Weekly Management of Technician Capacity
- Key metrics on appointment fulfillment rate, on-site arrival rate, reasons for cancellations, and throughput
- Data transfer to your billing and device management system
- As-Built Documentation in GIS According to DVGW GW 120
- Handover to the network operator and on-call service
- Updating Your Rehabilitation Strategy in Accordance with DVGW W 403
How far in advance must a meter replacement be announced?
The meter operator must give advance notice of the installation—in practice, about three months in advance. This lead time is not an obstacle but rather a planning advantage: it allows enough time to schedule an appointment, send a reminder, and follow up a second time before the technician even sets out.
What happens if the customer doesn't show up for the appointment?
We document every attempt to contact the customer and follow a set escalation process. After the second unsuccessful attempt, a notification card with a self-booking link is sent. Only then is the case marked as unfulfillable and reported back.
Do you also handle the installation yourself?
Yes, upon request. Appointment scheduling and installation can be arranged separately or as a package. If you have your own installers, we’ll coordinate with your team and simply provide the appointment slots.
How quickly can you boot up?
That depends on the region and the available data. We usually need a few weeks' lead time for an initial pilot run. It takes longer to ramp up to full capacity after that, because the outreach letters, quotas, and route planning need time to settle in.
Is Your Rollout Off Schedule?
Talk to us. We’ll review your appointment fulfillment rate and the reasons for missed appointments and tell you where time is actually being wasted.
Do you have any questions? We’d be happy to answer any questions you may have about appointment management, scheduling, and smart meter rollout.